Training Process & Acceptance Standards
Six majors, each with a step-by-step work process and quality standards used as the reference for the online self-test and field work assessment.
Residential Electrical Installation
Work Process
- Site survey: mark positions of lights, switches and sockets
Use a tape measure and chalk line to mark the height of every point: switches at 130 cm, sockets at 40 cm, bed-side switches aligned with the bed edge. One missed point means re-chasing the wall.
- Conduit installation: chase and run conduits per PUIL, power & data separated
Fix conduits with clips every 80 cm so they do not sag. Keep power and data lines at least 30 cm apart; wrap data conduits with foil where they cross to avoid signal interference.
- Wiring & termination: tight terminals, live-neutral-earth clearly separated
Strip insulation max 1 cm and crimp terminals until they pass a pull test. Keep colours consistent: live red/brown, neutral blue, earth yellow-green. Mixed colours make future maintenance unreadable.
- Panel assembly: install MCB per circuit group and label each group
Size each MCB to its load: lighting 6A, sockets 16A, a dedicated 16A for AC. Label every group inside the panel so a tripped breaker can be traced at a glance.
- Earthing test: measure earth and insulation resistance
Use a 500V insulation tester between conductors and to earth; reading must be at least 0.5 MΩ. Measure earthing resistance with an earth tester, standard ≤4 Ω. Do not proceed to live testing if this fails.
- Live test: energize circuit by circuit, check function and panel temperature
Energize circuits one by one and test every point with a voltage pen. After 30 minutes touch the MCB surface: warm is normal, abnormally hot means switch off immediately and trace the fault.
Acceptance Standards
- Every point works normally, faceplates tight
Toggle every point 5 times, check socket polarity with a phase tester, and the faceplate gap must not accept a name card.
- Circuit load matches MCB rating, no overload
Match each circuit load to its calculation: keep one socket group under 2000 W so the MCB does not run hot near its rating.
- Insulation resistance at least 0.5 MΩ
0.5 MΩ is the floor; humid circuits like bathrooms should reach 1 MΩ. Below standard, keep hunting for the damp or damaged spot.
- Conduits secured, wire fill max 40% of conduit area
Shake each conduit by hand: it must not move. Keep wire fill under 40% of the conduit area, or pulling new wires later becomes impossible.
- 1-hour live run without tripping or abnormal heat
Run full load for 1 hour: no tripping and no abnormal temperature rise at joints (by hand or thermal camera). Passing this run is the sign-off for handover.
Tiling & Plastering
Work Process
- Base preparation: clean dust & oil, remove loose parts
Scrape off dust and grease, chip out loose sections and re-plaster. A weak base will peel off whole tiles no matter how well they are laid.
- Set out & layout: establish reference lines and joint pattern
Start the layout from the main wall seen on entry, putting cut tiles in hidden corners. Snap cross reference lines so rows stay true over distance.
- Dry fit: match pattern and direction, arrange tight joints
Dry-fit first to check colour variation and pattern direction, including under artificial light. Pre-view all cut tiles in hidden areas.
- Tile fixing: thin-bed method, press fully until mortar squeezes out
Thin-bed fixing: comb the mortar evenly with no voids, press and rub until mortar squeezes into joints. Check flatness with a straightedge and tap with a rubber mallet as you go.
- Grout & cure: clean joints, grout neatly, protect from vibration for 24 h
After 24 h clean the joints and grout, removing all spacers. Cure for 24 h with no vibration or load — disturbed grout cracks easily.
- Clean & handover: clean surface, protect finished work
Wipe off grout haze with a wet sponge and cover the surface until handover. Scratched new tiles during finishing works are the most common dispute.
Acceptance Standards
- Hollow tiles max 5%, no hollow sound (tap test per tile)
Tap every tile with a striker: hollow sound means void. Standard allows max 5% hollow; centre-void tiles must be redone, thin edge hollows may pass.
- Flatness within 3 mm per 2 m straightedge, joints even and straight
Lay a 2 m straightedge in every direction: gap max 3 mm. Grout lines must read as straight rows with no lippage between tiles.
- Internal/external corners square, cut edges without chips
Check inner/outer corners with a square: they must be plumb. Cut edges must be free of chipped glaze — edge cracks show badly under lighting.
- Grout full and dense, no gaps or stains
Grout filled to the base, continuous with no pinholes. Clean residue within 1 hour of grouting; once cured, grout haze is very hard to remove.
- Surface clean, water flows freely to floor drain (water test)
Pour-water test: flow smoothly to the floor drain with no ponding. Bathrooms need 1–2% slope; even small puddles mean the floor needs correction.
Professional Painting
Work Process
- Protect the area: cover glass, doors, floors and fixed items
Cover glass, doors, floors and fixed furniture with masking film. Good protection lets you work fast without fear of stains.
- Base check: repair cracks, scrape off peeling paint
Bridge cracks with mesh tape and scrape flaking paint back to solid wall. A crack merely painted over reappears within 2–3 months.
- Putty: 1–2 leveling coats, sand after drying
Apply 1–2 coats of putty, let it cure hard, sand with 240 grit. Check for waves with side lighting — the fastest way to find uneven spots.
- Primer: roll anti-alkali primer evenly
Roll the anti-alkali primer evenly with no missed spots. Skipping primer causes alkali stains on the topcoat that extra coats cannot fix.
- Top coat: 1–2 coats, cross-rolling technique
Finish with 1–2 coats using cross (W) rolling, keeping roller loading even. Join areas while the paint is still wet to avoid lap marks.
- Clean & inspect: remove covers, check even color
Peel masking tape right after the paint skins over, pulling slowly at 45°. Check colour consistency in both daylight and lamplight.
Acceptance Standards
- Consistent even color, no sagging, no thin/see-through patches
Inspect walls under side light: no runs, no show-through, no colour difference between sections. Check twice: straight-on and at an angle.
- No visible brush/roller marks or grit
At 1.5 m distance there are no brush/roller marks or coarse grains. Grains usually come from sanding dust not cleaned before painting.
- Internal/external corners straight, no color shading at corners
Snap chalk lines on corners: they must be straight. Colour separation lines must not bleed into each other; use a straightedge or tape when cutting in.
Aluminium Frames & Windows
Work Process
- Re-measure: confirm opening sizes and swing direction
Measure opening width and height at 3 points (top-middle-bottom) plus diagonals. Diagonal error over 5 mm means fix the opening first — even a precise frame will never sit true.
- Cut profiles: cut per shop drawing, square ends
Use a fine-tooth blade and cut each 45° mitre in one pass. File the cut edges smooth so assembled corners close tight.
- Corner assembly: crimp with corner machine and inject corner adhesive
Crimp corners with a corner machine and inject corner adhesive. Run a finger over the joint: no step allowed. White gaps are filled with tinted adhesive before crimping.
- Install hardware: hinges, locking points, rollers
Tighten every hinge screw fully with no stripping, lock points aligned with strike plates. Adjust rollers until sliding is smooth with no jumping or noise.
- Set into opening: level & plumb correction, solid anchoring
Once level and plumb, anchor the frame with expansion bolts or fixing plates and fill the gap fully. A loose frame invalidates the whole installation.
- Test & handover: smooth operation, sealed with silicone
Operate 20 cycles smoothly, silicone inside and out continuous and full. Keep the unit unloaded and dry for the first 48 h so adhesive cures properly.
Acceptance Standards
- Level/plumb deviation max 2 mm per meter
2 m straightedge plus feeler gauges on the frame face: level/plumb within 2 mm per metre. Beyond that doors hang heavy, sliders stick, and drafts appear.
- Smooth operation without sticking, locking points fully engage
Handles open and close smoothly and every locking point fully engages. Test all four corners of the sash, not just one.
- Assembled corners gap-free, 45° joints flush
Inspect 45° joints against light: no gaps. Finger check: no step. Hairline gaps leak air and whistle in rain.
- Silicone continuous and even, no missed sections
Silicone continuous and even, no gaps or bubbles, width-to-thickness about 2:1. A break in the bead is a water path.
- No scratches or deformation, full hardware functioning
Profiles free of scratches and bends; protective film stays on until handover. Check every hardware item one by one and operate it.
Prefab Partition & Ceiling
Work Process
- Set out lines: wall position and ceiling height lines
Chalk the wall position on floor and ceiling, mark ceiling height with a level and keep it continuous around the room. A skewed start line skews the whole ceiling.
- Frame installation: edge, main & furring channels, level corrected
Install edge frames first, main channels spaced max 1200 mm. Tighten and adjust every hanger with a level; an uneven frame means uneven panels, period.
- Concealed services: run conduits first and inspect
Run and live-test all wiring before closing the boards. Once gypsum is on, changing a run means opening panels all over again.
- Board fixing: gypsum/PVC boards staggered, screw spacing per spec
Fix gypsum panels offset (brick pattern), never in line. Screws: 150 mm from edges, 200 mm in the field, heads slightly recessed without tearing the paper.
- Jointing: joint tape then joint compound
Fill joints with compound and embed paper tape while compacting, then apply a second coat. Two boards butted in line without tape will crack, guaranteed.
- Final preparation: sanded smooth, ready for paint
Spot-prime screws with anti-rust paint, skim flat, then sand with 240 grit until side lighting shows no shadows.
Acceptance Standards
- Ceiling surface flat, within 3 mm per 2 m straightedge
2 m straightedge on the ceiling face: max 3 mm. Side-lit strip lights are the fastest way to reveal uneven areas.
- Boards staggered, screws flush and rust-treated
Screws evenly placed with anti-rust spot treatment. Untreated rust points bleed through paint as yellow stains.
- No cracks at joints, compound full
Joints crack-free with full compound. Re-inspect 1 month after handover: movement cracks usually only show by then.
- Partition plumb within 3 mm per 2 m, glasswool fully filled (if designed)
Partitions plumb within 3 mm per 2 m. Glasswool (when specified) filled completely with no gaps; even small voids noticeably weaken sound insulation.
- Access panels and light points positioned accurately
Access panels, light points and AC grilles match the working drawings with clean cut edges. Off-position cutouts leave lights and grilles visibly misaligned.
AC Service & Installation
Work Process
- Position survey: confirm indoor/outdoor unit locations and drain route
Indoor unit away from right above the bed (drips and noise), outdoor unit needs 30 cm of ventilation clearance. Condensate line slopes to a drain, not hanging mid-wall.
- Bracket installation: drill and fix brackets, level and solid
Anchor brackets with full expansion bolts and stand on them to confirm zero movement. Corroded brackets are the number-one cause of falling outdoor units.
- Pipe connection: flare copper pipes, route pipework neatly
Flare copper pipes with a proper flaring tool: the flare rim must be smooth and crack-free. Bend with a bender, never by hand — hand bends kink and restrict flow.
- Vacuum: vacuum at least 15 minutes, hold pressure
Vacuum at least 15 minutes to -0.1 MPa and hold: a steady needle means leak-free. Any rise means a leak — find it before charging refrigerant.
- Test run: charge refrigerant by weight, measure air temperature split
Charge refrigerant to nameplate spec (or by pressure/superheat), then measure the inlet-outlet air temperature difference. Below standard means the charge is off.
- Handover: explain usage and maintenance schedule
Show remote use and filter-cleaning cycles, hand over the warranty card, and dress the pipe run with cable ties. A tidy pipe run is the showcase of installation quality.
Acceptance Standards
- Indoor/outdoor units solid, brackets carry the load
Indoor unit firmly on the wall without wobble, outdoor unit double-nut locked with rated brackets. Check firmness by hand, not by eye.
- Flares crack-free, joints pass leak test
Flare rims crack-free; soap-test or leak-detect every joint: zero bubbles. A joint that only looks fine can still fail the leak test.
- Vacuum passes standard (−0.1 MPa held 15 minutes)
Vacuum holds -0.1 MPa for 15 minutes with no needle rise. A short vacuum leaves moisture that clogs valves and wears the compressor.
- Cooling test: supply/return air temperature split at least 8°C
After 15 minutes in cooling mode, inlet-outlet Δt at least 8°C; heating at least 16°C. Below that, check refrigerant charge or airflow.
- Condensate drains freely without dripping, pipework neat
Pour water into the drain tray: flows freely with no wall drips. Pipe runs dressed neat and strapped — this is also the aesthetic score of the install.
Failed the self-test? You may retake it anytime. A result above 80% helps the training team schedule your class.